In 2023, 300+ A100/H100 GPU servers, 93 cabinets, 839 devices, 7,982 cablings, and 16,430 labels were delivered to customer J in Chicago, USA.
Service content: Provide customers with the overall delivery and implementation of GPU computing power cluster equipment, including: complete cabinets, network equipment deployment, GPU\CPU server modification, power testing, hardware testing, shelf system debugging, cabinet consolidation, wiring, transportation and customs clearance. Serve.

  1. Actual construction period of the first and second phases: 39 days
  2. The first and second phases of construction start time: September 1, 2023.
  3. Completion time: October 9, 2023.
  4. Actual construction period of the production cluster: 9 days
  5. Production cluster start time: October 5, 2023
  6. Completion time: October 14, 2023.

EZSVS JAPAN


click to enter
Founded in 2017, EZSVS JP is dedicated to providing end-to-end
comprehensive data center lifecycle services for clients in the internet,
OEM/ODM server manufacturing, and telecommunications sectors.
We collaborate extensively with ecosystem partners,offering
services related to infrastructure,supply chain,project implementation,
IT operations, and cloud intelligence.

This will close in 0 seconds

EZSVS SINGAPORE



click to enter

EZSVS is one of Singapore’s leading Internet Data Center (IDC) support service providers
with various branches in over 60 countries, catering to customers requiring innovative IT
solutions worldwide.

With our combined 16 years in the industry and technical experience,
EZSVS is able to provide our customers simple and hassle-free IT support and maintenance services.

This will close in 0 seconds